Span Bridge

Span Bridge Project Description

Construction of a short span bridge on Highway No. 211 over the Blackstrap Causeway, and for the CONSTRUCTION OF A GRADE RAISE AND SURFACING STRUCTURE; for a TOTAL DISTANCE OF 0.37 km.

  • Phase I will be defined as all Work other than the Sub-base Course In Place, Granular Base Course In Place, Asphalt Concrete In Place, Reclaimed Asphalt Concrete, Traffic Gravel Behind Construction Including Hauling and Site Restoration. Completion date of Phase I is March 31, 2020.
  • Phase II will be defined as Sub-Base Course In Place, Reclaimed Asphalt Concrete, Traffic Gravel Behind Construction Including Hauling. Completion date of Phase II is April 30, 2020.
  • Phase III will be defined as Granular Base Course In Place, Asphalt Concrete In Place and Site Restoration. Completion date of Phase III is June 15, 2020

See Details.